Change Order Pricing Calculator

Line Items
$
$
15.0%
10.0%
1.0%
Total Change Order Value$5,493.90
Direct Cost Subtotal$4,300.00
Overhead$645.00
Profit$494.50
Bond Adjustment$54.40
Cost per Day (Schedule Impact)$1,098.78

Item Breakdown

DescriptionMaterialLaborDirect Total
Additional framing$2,000.00$1,800.00$3,800.00

This change order calculator builds a defensible price for added or deleted scope by stacking direct costs and then layering the standard contractor markups on top. You enter line items for material and labor, add lump-sum equipment and subcontractor costs, and the tool applies overhead, profit, and a bond adjustment in sequence. It also divides the total by any schedule impact in days to show a cost-per-day figure useful for time-and-materials negotiations.

Formula

Total = ((Direct × (1 + OH)) × (1 + Profit)) × (1 + Bond), where Direct = Material + Labor + Equipment + Subcontractor

Direct
Direct cost subtotal: material + labor (hours × rate) + equipment + subcontractor
OH
Overhead rate as a decimal (e.g. 15% = 0.15)
Profit
Profit rate as a decimal, applied after overhead
Bond
Bond/insurance adjustment rate as a decimal, applied last

How it works

  1. Add one or more line items, each with a description, material cost, labor hours, and labor rate. Labor cost for a line is hours multiplied by rate, and the direct cost of the line is material plus labor.
  2. Enter lump-sum equipment and subcontractor costs. These are added to the summed material and labor totals to form the direct cost subtotal.
  3. Set the overhead, profit, and bond rates (defaults 15%, 10%, and 1%). The calculator applies them in a compounding chain — overhead on direct cost, profit on the overhead-inclusive subtotal, then bond on the profit-inclusive subtotal — and divides the grand total by the schedule impact in days for a cost-per-day value.

Worked example

A change order with $5,000 material, 40 labor hours at $65/hr, $3,000 equipment, and $8,000 subcontractor, using default 15% overhead, 10% profit, and 1% bond, with a 10-day schedule impact.

  1. Labor cost: 40 × $65 = $2,600. Direct subtotal: 5,000 + 2,600 + 3,000 + 8,000 = $18,600.
  2. Overhead: 18,600 × 15% = $2,790, giving a subtotal of $21,390.
  3. Profit: 21,390 × 10% = $2,139, giving a subtotal of $23,529.
  4. Bond: 23,529 × 1% = $235.29, giving a total of $23,764.29. Cost per day: 23,764.29 ÷ 10 = $2,376.43.

Total change order value is about $23,764.29, with roughly $2,376.43 of cost attributed to each of the 10 added schedule days.

Frequently asked questions

Why are overhead, profit, and bond applied in sequence rather than all at once?
The markups compound: overhead is added to the direct cost, profit is then calculated on that overhead-inclusive subtotal, and the bond adjustment is applied to the profit-inclusive subtotal. This mirrors how most prime contracts and the standard markup chain price a change order, so the bond covers the full marked-up amount.
What overhead and profit rates should I use?
Many contracts cap change order markups, commonly around 10–15% for overhead and 10% for profit, though the exact limits are set in the contract general conditions. The calculator defaults to 15% overhead, 10% profit, and 1% bond, but you should override these to match your specific agreement.
What does the cost-per-day figure represent?
It is simply the total change order value divided by the number of schedule-impact days you enter. It is a quick reference for negotiating time-related compensation, not a substitute for a detailed extended-overhead or delay-damages analysis.
Does this calculator handle deductive (credit) change orders?
The tool is built for additive scope and clamps negative cost inputs to zero. For a deductive change order, price the removed scope as a positive value and apply it as a credit in your contract documents, since markups on credits are often negotiated differently.